For growing construction firms, scheduling is often one of the first systems to show signs of strain.

As project sizes increase, timelines compress, and subcontractor coordination becomes more complex, informal, or poorly structured schedules quickly lose credibility. At Vail Custom Builders (VCB), a residential construction firm known for “building and remodeling homes of uncompromising quality,” leadership recognized that scheduling inconsistency was limiting performance.

The turning point came with the arrival of David Hanen, Director of Construction, who brought with him not just a new scheduling tool but a fundamentally different philosophy around how schedules should be built, maintained, and used.

The challenge: inconsistent schedules and limited visibility

Before David joined the organization, VCB relied primarily on a popular program to manage construction schedules. While widely used, schedules were not consistently tied, sequenced, or maintained. Dependencies were often inaccurate, logic was incomplete, and schedules functioned more as rough timelines than true management tools. This lack of structure made it difficult to forecast issues, coordinate subcontractors effectively, or confidently communicate completion dates. Leadership knew scheduling was a problem but fixing it required both technical expertise and organizational buy-in.

David had extensive prior experience with Elecosoft’s Powerproject, dating back to 2016. His background also included years working with another scheduling tool, making the transition to Powerproject challenging at first. “When I first started using it, it was difficult,” he recalls. “Coming from the previous program, the workflow felt different. At first, I thought it was better suited for small schedules or remodels.”

That perception changed as he pushed deeper into the platform. Over time, David used Powerproject to successfully schedule projects ranging from $25 million to over $100 million, managing complex sequencing, multi-level activities, and long-duration builds. “Once I really understood how it worked, I realized there was no reason to switch, unless something better was invented, which I can’t imagine.”

Asta Powerproject, a project management software designed for construction professionals

Central to David’s approach is a strict rule: schedules must reflect reality, not optimism. “A schedule is not a wish list,” he explains. “You can manipulate a schedule however you want, but if you’re not honest with it, you won’t get honest results.”

Rather than treating schedules as static documents, David emphasizes accuracy based on real-world inputs: subcontractor availability, supply chain constraints, procurement timelines, and field conditions. Without that discipline, even the most sophisticated software loses value.

Implementation: collaboration over command

When David joined VCB, he immediately began migrating all active project schedules into Powerproject. However, he was careful not to impose change unilaterally. “There was some initial pushback,” he admits. “But my approach was simple: I just let everyone know I was here to help them create more effective, more accurate schedules.”

Rather than rebuilding schedules in isolation, David worked directly with project managers and superintendents to establish logical flow and sequencing. Once schedules reached a manageable state, the process expanded outward. Subcontractors were brought in for multiple sequencing and schedule meetings, often six or seven per project. Together, the team broke down high-level activities into smaller, trackable components and established realistic durations. Crucially, this happened weeks before work began.

“I’m a big believer in early subcontractor buy-in,” David says. “We don’t want to tell subs how long they have to complete their work. We prefer to ask them.”

Powerproject is now used consistently across VCB projects. David reviews each active schedule at least once or twice per week per project, using it to look ahead for material procurement, subcontractor coordination, and sequencing conflicts. Weekly job walks include structured team meetings with the project manager and superintendent. Schedules are updated collaboratively, printed as four-week “look-aheads,” and used as active planning tools, not archival documents. Training has been gradual and deliberate. While project managers now log in regularly to review upcoming dates and constraints, David remains closely involved, guiding updates and reinforcing best practices.

“Back in 2016 it took me two full projects before I felt fluent,” he notes. “So, I’m patient. I’m aware that this is an ongoing learning process.”

Measurable results

One standout example involved a developer-led duplex project originally scheduled as a two-year build. Through disciplined weekly updates, subcontractor accountability, and accurate sequencing in Powerproject, the team was able to move the end date forward significantly, recovering substantial time without sacrificing quality. The impact wasn’t tied to software alone.

“It’s Powerproject plus the system,” David emphasizes. “Weekly updates, subcontractor buy-in, and the ability to clearly see every activity and every logic tie in the schedule.”

VCB plans to expand Powerproject usage into smaller projects such as kitchen remodels and decks, as well as future commercial work. As the company grows, more project managers and superintendents will be trained, with the preference being one Powerproject license per project to maintain accountability and clarity. Ultimately, the transformation at VCB illustrates that scheduling success is not about software adoption alone; it’s about discipline, transparency, and collaboration.

“When people understand the flow, the logic, and the purpose,” David says, “the schedule stops being a document and starts being a tool.”