Buffalo’s $2.1B Highmark Stadium Reaches Halfway Mark With Ceremony
Subscribe to our free newsletter today to keep up-to-date with the latest construction news.
Buffalo’s $2.1 billion Highmark Stadium project reached a critical construction milestone on April 4, 2025. The topping-out ceremony marked the placement of the final steel beam, bringing the build to 50 percent completion. Located in Orchard Park, New York, the venue is on schedule to open before the 2026 NFL season.
With a seating capacity of 62,000, the new stadium reflects a shift toward more compact, fan-focused NFL venues. Construction began about 20 months ago, progressing through Buffalo’s winter conditions with major excavation and structural work. Crews have removed 742,000 cubic yards of dirt and poured over 46,000 cubic yards of foundation concrete.
The structure now includes more than 22,000 pieces of steel, weighing over 25,000 tons. Sixty percent of the steel was sourced from New York State, and nearly all materials were manufactured in the United States.
Features built for climate and comfort
Buffalo’s stadium is being designed to handle the region’s weather while enhancing the fan experience. A 360-degree canopy will cover 65 percent of seating, offering protection from wind, snow, and rain. It also helps trap and reflect sound back toward the field, creating a louder environment for home games.
The stadium will feature heated concourses and selected seating areas to provide comfort in cold months. One of its most advanced features is a snow melt system, the largest of its kind on any stadium. Sensors in the roof detect snowfall and trigger an automated response to melt snow buildup.
Fans will also benefit from upgraded technology, including two massive video boards and a high-fidelity sound system. From the upper decks, spectators will have views of downtown Buffalo, Lake Erie, and the surrounding hills.
Public-private investment and local impact
The stadium’s total cost has increased by $560 million above original estimates. That overage is being covered by team owners Terry and Kim Pegula. Public funding contributes $850 million, with $600 million from New York State and $250 million from Erie County.
The stadium is projected to generate $2.1 billion in long-term economic value for the state. During construction, it will create about 10,000 union jobs across trades including steel, concrete, electrical, and logistics. Local hiring and business inclusion have been a focus throughout the project. Governor Kathy Hochul has positioned the project as a cornerstone for Western New York’s economic future, citing both job creation and infrastructure renewal.
Where it fits among NFL stadiums
Highmark Stadium will be smaller than venues like SoFi Stadium in Los Angeles or Allegiant Stadium in Las Vegas. SoFi holds around 70,000 fans and was privately financed. Allegiant seats about 65,000 with minimal public funding.
Buffalo’s approach favors resilience and regional fit over luxury. The stadium’s design focuses on climate response, sightlines, and community utility. Although it will support non-NFL events, including concerts and festivals, it is built primarily for football.
With the steel frame in place, work now shifts to canopy assembly, interior finishes, and facade installation. Precast materials are being mounted to shape the exterior, followed by architectural panels, perforated metal, and glass.
Upcoming construction milestones include the integration of lighting, sound systems, and final infrastructure. The venue will also secure partnerships for non-game-day programming to ensure it serves Western New York beyond the regular season.